lorient three

timescale

The first action in the transformation of the bunkers would be the removal of substantial parts of the massive concrete roof, allowing the introduction of natural light into the core of the structures. Openings would be formed in fifteen metre wide strips corresponding to the cell dimensions of the bunkers running with the grain of the cells in the case of K1 and K2, and across the grain of the cells in K3. The length of the strips shown varies from twenty-two metres up to ninety five-metres. The cut edges of these new openings would reveal the layered construction of the bunker roofs and would act as 'reveals' reflecting light down into the cells below. Eight cells out of a total of twenty would remain un-altered. The study model indicates the quality of light which could be achieved with these new openings. Functions would be housed in new enclosures built both within and on top of the existing bunkers . Each of the three main buildings would have lift and stair access to all levels including the roofs. In addition building K2 will have a new external stepped ramp to allow public pedestrian and restricted vehicle access onto the roof of the building.

 

 

site active as french naval yard

 

 

 
 

instigation of redevelopment programme

 

 
 

temporary relocation of K3 and K2 tenants to allow construction work

 
   
  new road infrastructure and landscape infrastructure phase one  
 

construction of new service cores to K1 and K3

 

 
  new openings in perimeter fence - direct access to pourquoi pas and south quay  
  excavation/partial demolition of K1 and K3  
 

new slipway construction

 

 
  establishment of first roof buildings  
   
 

institution of public events programme

 

 
 

road infrastructure - phase two

 

 
  K2 (or K1) public ramp construction  
  construction of first internal structures within bunker cells  
   
 

completion of new riverbus jetty

 
 

remaining building plots and landscape infrastructure

 

 
 
completion of tram link
 
   
   
demolition of earmarked existing structures complete
  expiry of plastimo lease  
   
 
extended development period for new technical support workshops